NEXTDC shares plunge 44% as power delays expose AI data centre bottleneck

NEXTDC’s downgrade is a stark example of a risk investors have tended to treat as theoretical: that grid access and local opposition, not customer demand, cap how fast data centre capacity can be built. The read-through extends well beyond Australia, as operators and AI cloud providers globally depend on utilities and planning authorities that move more slowly than hyperscaler spending plans. It echoes the warning in Anthropic’s draft IPO prospectus, reported this week, that resistance to data centres is becoming more organised across jurisdictions. Investors may now apply a larger discount to contracted-but-undelivered capacity across the sector, particularly where projects depend on new grid connections.

–

NEXTDC had the customers and the contracts, but not the electricity, and its 44% share collapse shows the AI build-out now runs only as fast as the local grid and the local council allow.

Summary:

  • NEXTDC shares fell 44% in early trading after the company cut its FY27 guidance
  • Underlying EBITDA guidance was lowered to A$245 million to A$265 million, from A$385 million to A$410 million; net revenue guidance cut to A$475 million to A$500 million, from A$615 million to A$640 million
  • The downgrade stems from delays to grid works by Jemena Electricity Networks for the M3 Melbourne data centre, suspended in September after community opposition, safety concerns and a lack of council consent
  • Works are not expected to restart before February 2027, with extra grid supply now expected in FY28; the affected contracts were worth about A$140 million in prior guidance
  • All new development projects and land purchases are on hold, and FY27 capex guidance was cut to A$4.5 billion to A$5 billion
  • NEXTDC reported about A$8.7 billion of liquidity, including about A$1.3 billion in cash, and remains within its debt covenants

Access to electricity has emerged as a hard limit on the data centre build-out, after Australian operator NEXTDC slashed its earnings forecast because the power needed for a major Melbourne facility will arrive a year later than planned.

NEXTDC shares plunged 44% in early trading after the company cut its fiscal 2027 underlying EBITDA guidance to A$245 million to A$265 million, from A$385 million to A$410 million. Net revenue guidance was lowered to A$475 million to A$500 million, from A$615 million to A$640 million.

The problem is not demand. The capacity at its M3 Melbourne site remains contracted to customers. Instead, grid works being carried out by Jemena Electricity Networks were suspended in September following community and stakeholder opposition, safety concerns and the absence of local council consent while further consultation takes place. Chief executive Craig Scroggie said Jemena did not expect the works to restart before February 2027, pushing the next increase in grid supply to M3 into fiscal 2028.

That delay defers the delivery and billing of contracted capacity that had contributed about A$140 million to both revenue and EBITDA in the previous forecast. The contracts include service-level credits for delays and, in some cases, termination rights.

Planning approval is also slipping. A Victorian government decision on later stages of the M3 development is now expected in 2027, with the state entering caretaker conventions on 3 November ahead of its 28 November election.

NEXTDC has put all new development projects and land acquisitions on hold, focusing spending on capacity due over the next 12 to 18 months, and its board will consider selling development sites not needed in the near term. Fiscal 2027 capex guidance was cut to A$4.5 billion to A$5 billion, from A$5.25 billion to A$5.75 billion. The company said it had about A$8.7 billion of liquidity at 30 September and remains within its financial covenants.

The episode highlights a risk that extends well beyond one company or one city. As AI drives record investment in computing capacity, the pace of delivery increasingly depends on utilities, planners and local communities. Anthropic’s draft IPO prospectus, reported this week, flagged growing and more coordinated political resistance to data centres as a business risk. NEXTDC’s downgrade suggests investors may need to price that risk into contracted capacity across the sector.

This article was written by Eamonn Sheridan at investinglive.com.